Monday, January 9, 2012

1/9/12

Not a whole lot to show with pictures, but a lot is being done. The plumbing and heating are progressing with the electrical set to start later this week. Lights have been set up inside, so we can finally go to the house on a weekday without having to worry about interupting the work. We also still haven't passed court in Ethiopia. We're trying to wait patiently which is a lot easier said than done. The third and final bathtub is in - this one in the basement
The framing in the basement is being finished. Here you can see the final wall in the guest bedroom has been added.


The exterior at night with the lights on. Light haven't been brought upstairs so that remained dark.