Almost two months in. The second floor has been started. Before they can really get into the second floor the back deck needs to get up since it helps support the second floor.
Wednesday, October 26, 2011
Saturday, October 22, 2011
Another good week
Another week down. The main level is now framed in. Next week they'll start going up to the second floor. I've also tried adding a couple videos.
Monday, October 17, 2011
More Progress
After a weekend of some nasty weather things cleared up a bit, so Monday saw another day of good progress. Nearly half of the perimeter of the main floor is now framed in. Things are definitely beginning to take shape.
The garage floor will hopefully be laid soon. The trench is for the garage footings. You can see that the front wall of the house is pretty much in place.
Tuesday, October 11, 2011
Moving on up
Before we get to the updated house pictures let's get to the important stuff. Yesterday morning we received a referral for a beautiful 10 month old girl. She appears to be a very healthy young girl and we can not wait to get her home. She has been described as fast, strong, and energetic, so hopefully she'll be able to hold her own with Addy. Now the race is on to see what happens first-the house gets finished or we bring home our little girl.
Saturday, October 8, 2011
Framing has begun
We anticipated great things this week. With great weather a lot of work has been accomplished. The mason wasn't able to get a load of concrete until Tuesday and it took a little longer for the concrete to dry than expected, but it was still a very productive week.
Monday, October 3, 2011
Great weather this week -- expecting great things!
The basement floor should be poured tomorrow. We can start to visualize our backyard. Things are coming along. The weather forecast is good this week. They should start framing in on Wednesday. Still no word on our referral.....
The ground floor is ready for the concrete to be poured.